Alira at Berwick Community Update

Hi there,

We are getting in touch to provide you with an update on the Greaves Road and Berwick Springs Promenade roundabout.

Roadworks on the southern side of the roundabout are progressing well, with pedestrian footpaths now complete and asphalt due to be laid in the next few weeks. Nature strip work has begun on the southern side with landscaping and garden bed preparation occurring in the coming days. 

All major reconstruction works are now complete on the Berwick Springs bluestone walls, with only landscaping works remaining. Once complete, the Berwick Springs entrance will be re-open for pedestrian traffic.

Traffic conditions are not expected to change in the coming weeks, however, are expected to improve upon the construction’s completion in two months’ time. As such, we ask all drivers and pedestrians to pay close attention to signage, obey traffic signs and remain patient and respectful towards workers onsite during this time.

The new Greaves Road and Berwick Springs Promenade roundabout construction is running to schedule and is expected to be completed in October 2019.

Stay informed

Our next Alira at Berwick newsletter – outlining construction updates and progress of the roundabout – will be distributed digitally in September.

If you know any residents who would like to receive this newsletter, they can register here.

If you have questions or queries concerning community construction updates, please contact Martin Gaedke, Moremac Property Group Project Director on martingaedke@moremac.com.au or 9851 3303.